MILLENNIUM PARK REUSE EXTENSION - PHASE 1 - PROJECT 142173410
INVITATION TO BID
DATE: March 23, 2023 Project Number: 142173410
NOTICE IS HEREBY GIVEN that the City of Wildwood will receive sealed bids for construction of the Millennium Park Reuse Extension- Phase I. All contractors licensed by the State of Florida are hereby invited to submit a bid on the above referenced project. Bids will be received until 3:00 PM, E.S.T., on May 4, 2023, at the following address: Wildwood City Hall, 100 N. Main Street, Wildwood, FL 34785. For more information, contact Stacy Boney, Kimley-Horn and Associates at (352) 438-3000.
DESCRIPTION OF WORK: All work for the Project shall be constructed in accordance with the Drawings and Specifications prepared by the Engineer. Bids shall be submitted for furnishing, delivering, and installing all materials, equipment, and services, including labor for the Work, which generally involves the following activities:
Construction of approximately 2,800 Linear Feet (LF) of 12” PVC reclaim main from an existing hydropneumatic tank in Millennium Park to the southeastern corner of Huey Street and St. Clair Street. Construction of approximately 1,000 LF of 4” PVC reclaim main to a stub out located at the southwestern border of Millennium Park.
CONTRACT TIME: Construction time to achieve Substantial Completion is 120 consecutive calendar days from the date of the Notice to Proceed, with an additional 30 consecutive calendar days to achieve Final Completion. Total construction duration is 150 consecutive calendar days.
PROJECT MANUAL AND DRAWINGS: Copies of the Project Manual and Drawings are available for review at the City of Wildwood City Hall or the Office of the Engineer (Issuing Office). Bid packages may be obtained by contacting the office of the Engineer via email:
Kimley-Horn and Associates, Inc.
1700 SE 17th Street, Suite 200
Ocala, Florida 34471
352-438-3000
E-mail: stacy.boney@kimley-horn.com
All bids shall be prepared using the Project Manual and Drawings. Addenda will be sent via e-mail to all documented plan holders up to seventy-two (72) hours before the Bid closing time. The Owner/Engineer is not responsible for delivery of addenda to prospective bidders.
PRE-BID CONFERENCE: A non-mandatory pre-bid meeting will be held for this project at 11:00 AM on April 6, 2023, at the City of Wildwood City Hall, 100 North Main Street, Wildwood, Florida 34785.
BID SECURITY: A 5% bid security is required for this project, to be submitted with bids.
PERFORMANCE AND PAYMENT BOND: The Owner will require that the Contractor furnish a Performance and Payment Bond in an amount equal to 100% of the Contract Price. All Payment and Performance Bonds shall be secured from or countersigned by an agency or surety company recognized in good standing and authorized to do business in the State of Florida.